Unit 2, Harmony Court, Govan
End of tenancy dilapidations works.
Following a competitive tender bid, we were delighted to be appointed to carry out dilapidations works at Harmony Court on behalf of the Landlord, Staples UK.
Works externally included cladding repairs; over sheeting of the main roof, new gutters and flashings; brickwork repairs and re-painting.
Internally, works included stripping out of the unit; preparation and re-painting of the steel frame and internal walls including blockwork; preparation of the concrete floor and subsequent decoration; and internal decoration generally.
Our client was delighted with our project management and the finished product.
Client | Lead Consultant | Sector |
Staples UK | Avison Young | Commercial |
Duration | Principal Contractor | Value |
8 Weeks | Cosmos Projects | £108k |
Let's get started
Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua.
Your World Matters to Us.
Cosmos Projects Ltd recognises that quality, health, safety and environmental matters are key to maintaining customer satisfaction and we recognise our role in ensuring a safe and healthy working environment for both our customers and our employees.
Cosmos Projects Group
Latest Articles
COSMOS PROJECTS ARE FULLY ACCREDITED WITH A NUMBER OF ORGANISATIONS
Cookie Policy
Find out more about how this website uses cookies to enhance your browsing experience.